Districts Impacted
Counties Impacted
Greene
Route Impacted
413
Work Type
Bridge Replacement
Planning Phase
Project Milestones
Complete
Virtual Public Meeting
Monday, January 30 - Friday, February 10, 2023
Public Meeting
4:30-6 p.m., Thursday, February 20
Location: Springfield-Greene County Botanical Center, 2400 S Scenic Ave, Springfield, MO 65807
Location: Springfield-Greene County Botanical Center, 2400 S Scenic Ave, Springfield, MO 65807
Construction
Winter 2024/Spring 2025
Construction Completion
Winter 2025
Project Facts:
- Replace Missouri Route 413 (Sunshine Street) bridge over MNA Railroad in Springfield
- Add/improve pedestrian facilities on both sides of roadway from Scenic Avenue to Marion Avenue
Construction: Spring 2025
Estimated total project cost: $5,888,000
Completion Date: Winter 2025
Bridge Facts:
- Bridge built in 1963
- Bridge carries 26,164 vehicles a day
- Old bridge 65 feet wide, 158 feet long
Traffic Impacts:
- MO 413 (Sunshine St) CLOSED from east of Scenic Avenue to west of Marion Avenue for up to 4 months during construction
- Detour: James River Freeway, Kansas Expressway, Chestnut Expressway, and US 160
Webform
Project Updates
-
MoDOT: Plans to Replace the Sunshine Street (Missouri Route 413) Bridge over MNA Railroad
Springfield – The public is invited to a virtual (online) public meeting starting Monday, January 30, to learn more about plans for the Sunshine Street (Missouri Route 413) Bridge Replacement and Pedestrian Improvements Project in Springfield, the...