What: Missouri Route 13 traffic shifted to the center turn lane at Wildwood Lane/Kissee Avenue intersection in Kimberling City
When: 6 p.m. Wednesday, August 25 until 6 a.m. Thursday, August 26
Details: Contractor crews removing old signals as part of the Missouri Route 13 Intersection Project in Kimberling City. New signals will be operational.
Traffic Impacts:
- Route 13 traffic shifted to the center turn lane alternating between northbound and southbound traffic at Wildwood Lane/Kissee Avenue intersection in Kimberling City
- Wildwood Lane will be closed at the Route 13 and Wildwood Lane/Kissee Avenue intersection at times
- Crews and equipment close to traffic
- Drivers urged to find alternate routes
- Electronic message boards located near the planned road work will alert drivers to any changes in the work schedule
- Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Project Summary:
- Contractor crews will remove the wooden posts, upgrade the signal and traffic detection loops and pavement stripe
- Contractor: Ewing Signal Construction of Nixa
- Completion date: December 1, 2021 (Contractor expects the project to be completed by early September)
- Total estimated cost: $204,160
(Weather and/or construction delays will alter the work schedule)
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram |YouTube)
(Take the Challenge! Buckle Up/Phone Down)
Districts Involved
Southwest
Published On