Where: Narrowed lanes, traffic shifts and nighttime lane closures on U.S. Route 60 (James River Freeway) between National Avenue and Campbell Avenue in Springfield
When: Beginning the week of March 20
What: Contractor crews are moving dirt and installing storm sewer pipes in the median. This is part of the U.S. ROUTE 60 (James River Freeway) Widening Project Between National Avenue & Kansas Expressway.
Traffic Impacts:
- Narrowed lanes and traffic shifts on Route 60 between National Avenue and Campbell Avenue in Springfield
- Nighttime lane closures on Route 60 between National Avenue and Campbell Avenue
- Drivers should not pass in the work zone due to narrowed driving lanes on Route 60
- Crews and equipment close to traffic in areas
- Signs and message boards will alert drivers approaching the work zone
- Drivers should look for alternate route
- Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or construction delays will alter the work schedule.
Project information:
Contractor: Capital Paving & Construction LLC, Jefferson City
Total estimated cost: $21 million
- Intersection Improvements at Campbell Ave are a cost share with the City of Springfield
Project Webpage & sign up for project updates: https://www.modot.org/us-route-60-james-river-freeway-widening-project
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram | YouTube)