Where: Ward Branch Greenway Trail CLOSED under U.S. Route 60 (James River Freeway) between National Avenue and Campbell Avenue, east of the Republic Road bridge over Route 60, in Springfield
When: 7 a.m. – 6 p.m. Thursday & Friday, April 13 & 14
What: Contractor crews are forming a beam over the Ward Branch Greenway Trail box culvert for the Route 60 sound walls. This is part of the U.S. ROUTE 60 (James River Freeway) Widening Project Between National Avenue & Kansas Expressway.
Traffic Impacts:
- Ward Branch Greenway Trail CLOSED under U.S. Route 60 (James River Freeway) between National Avenue and Campbell Avenue, east of the Republic Road bridge over Route 60, in Springfield
- Trail Open during nighttime hours
- Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or construction delays will alter the work schedule.
Project information:
- Contractor: Capital Paving & Construction LLC, Jefferson City
- Total estimated cost: $21 million
- Intersection Improvements at Campbell Ave are a cost share with the City of Springfield
- Project Webpage & sign up for project updates: https://www.modot.org/us-route-60-james-river-freeway-widening-project
END
(For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest)
(Follow MoDOT's Southwest District: Facebook | Twitter | Instagram | YouTube)
(Take the Challenge! Buckle Up/Phone Down)