Christian, Stone & Taney County – Drivers can expect lane closures and occasional traffic delays on Stone County Routes A and U, Christian & Stone County Route V and Christian & Taney County Route H for a resurfacing project beginning the week of October 9, the Missouri Department of Transportation said.
Routes will receive a new asphalt driving surface, guardrail and road markings in various locations. Crews will work during the hours of 6 a.m. – 6 p.m. from Monday – Friday.
Project Locations & Dates:
- Beginning Week of October 9
- Stone County Route A between Route K east of Hurley to the end of state maintenance
- Stone County Route U between Route A and Route M east of Highlandville
- Christian & Stone County Route V between U.S. Route 160/Missouri Route 13 south of Highlandville and Missouri Route 176 east of Galena
- Beginning the week of October 23
- Christian & Taney County Route H between Missouri Route 125 south of Chadwick and U.S. Route 160 north of Fordland
Traffic Impacts:
- Traffic reduced to one lane where contractor crews are laying asphalt
- Drivers will encounter flaggers and pilot cars where crews are working. Drivers should wait for the pilot vehicle before proceeding through the work zone or before entering the work zone from a side road.
- All lanes will be open during nighttime hours
- No signed detours
- Drivers should find alternate routes
- Signs and message boards will alert drivers approaching the work zone
- Crews and equipment close to traffic in areas
Weather and/or construction delays will alter the work schedule.
This project is part of Gov. Parson’s Rural Road program. The state’s approved Fiscal Year 2023 budget provided an additional $100 million in General Revenue for work on Missouri’s low volume rural roads. Using asset management data, MoDOT has identified approximately 1700 lane miles of low volume roads ranked in Poor Condition. By next summer, these 113 locations will receive resurfacing treatments of hot mix asphalt to improve the road conditions.
Project Information:
- Prime contractor: Capital Paving & Construction, Columbia
- Total project cost: $3 million
- Contract completion date: November 1, 2024
Sign up online for work zone updates here.
END
For more information, call MoDOT in Springfield at 417-895-7600 or visit www.modot.org/southwest
Follow MoDOT's Southwest District: Facebook | X | Instagram |YouTube
Take the Challenge! Buckle Up/Phone Down