Districts Impacted
Counties Impacted
Greene
Route Impacted
B
AB
266
Work Type
Intersection Improvements
Planning Phase
Project Facts:
- Build two single lane roundabouts on Missouri Route 266 to improve safety and traffic flow west of Springfield:
- Roundabout at Missouri Route 266 and Route B
- Roundabout at Missouri Route 266 and Route AB and North Farm Road 99
- Roadway lighting installed at roundabouts
- Approximately 7,300 vehicles per day use these intersections
Estimated total project cost: $4,184,000
Traffic Impacts:
- MO 266 to remain OPEN during construction
- Intersections will have single lane closures during construction of roundabout lanes
- North Farm Road 99 will be closed for up to 30 days
- Drivers should find alternate routes to avoid the work zone