Project Facts:
- Replace the concrete pavement on I-44 at MO 477/Mulroy Road interchange (mile marker 84) in Springfield
- Extend both eastbound I-44 ramps and the westbound I-44 on-ramp
- I-44 median drainage improvements at mile marker 84
- Seal the MO 477/Mulroy Road bridge deck/driving surface over I-44
-
Project will take approximately four months
Traffic Impacts:
- Phase 1: Beginning Friday, July 11
- Eastbound I-44 on and off ramps CLOSED at Missouri Route 744/Mulroy Road (exit 84)
- Ramps CLOSED up to 2 weeks
- Phases 2 & 3: Friday, August 5
- Beginning Friday, August 5 for up to 26 days
- Missouri Route 744/Mulroy Road Bridge CLOSED in Springfield
- Beginning Monday, August 8 for up to 23 days
- Eastbound I-44 traffic shifted up and over I-44 using the eastbound I-44 on and off ramps (mile marker 84)
- All lanes of eastbound I-44 CLOSED at Route 744/Mulroy Road (exit 84) CLOSED
- Drivers should expect traffic delays and narrowed lanes
- When this portion is completed, ramps will be closed for up to 3 days as crews restripe to new traffic configuration
- Beginning Friday, August 5 for up to 26 days
- Phase 4: August 10 - September 9
- Westbound I-44 on ramp will be CLOSED at Missouri Route 744/Mulroy Road (exit 84)
- Ramps CLOSED up to 2 weeks
- Crews and equipment close to traffic in areas
- Signs and message boards will alert drivers approaching the work zone
- Drivers should look for an alternate route
- Signed detours include: U.S. Route 65 Southbound, Missouri Route 744/ Kearney Street, Mulroy Road
- Weather or construction delays could alter the work schedule.
Construction: July 2021
This project also includes Chestnut Expressway Rebuild Project between I-44 and Broadview Place, which was completed June 17, 2022.
Estimated total project cost: $7 million (Chestnut Expressway Pavement Improvement, I-44 concrete rebuild and MO 744/Mulroy Road bridge)
Completion date: November 1, 2022
Project Updates/Traffic Alerts
-
MoDOT TRAFFIC ALERT: Eastbound I-44 Ramps (mile marker 84) & Mulroy Road OPEN
Where: Eastbound I-44 on- and off-ramps (mile marker 84) & Mulroy Road Bridge is OPEN
When: 12:30p Today, Friday, September 9
What: Possible lane and shoulder closures on eastbound I-44 on- and off-ramps as crews seed and mulch Monday, September 12...
-
MoDOT TRAFFIC ALERT: Traffic Pattern Changes at I-44 (mile marker 84) & Mulroy Road
Where/When:
- Eastbound I-44 ramps (mile marker 84) and the Mulroy Road Bridge will OPEN to traffic
- 5:30 p.m. Thursday, September 1
- No work planned over the Labor Day holiday weekend
- Eastbound I-44 ramps (mile marker 84) and the Mulroy...
- Eastbound I-44 ramps (mile marker 84) and the Mulroy Road Bridge will OPEN to traffic
-
MoDOT TRAFFIC ALERT: Traffic Pattern Changes at I-44 (mile marker 84) & Mulroy Road In Springfield
Where/When:
- Westbound I-44 on-ramp (mile marker 84) OPEN to traffic at 5 p.m. Thursday, August 25
- Both eastbound I-44 lanes (mile marker 84) OPEN to traffic Friday afternoon, August 26
- Eastbound I-44 on- and off-ramps (mile marker 84) CLOSED to...