Counties Impacted
Washington
Route Impacted
47
8
Work Type
Bridge Rehabilitation
Planning Phase

Project Summary

Route 8 & Route 47 Bridge Improvements

The Route 8 bridge over Bates Creek and the Route 47 bridge over Mineral Fork Creek are both being rehabilitated. While both bridges are in good condition, there are routine repairs needed to several components - and deck sealing where needed – that will extend the usable life of each bridge.


 

Route 8 Bridge

Work on the Route 8 bridge over Bates Creek, built in 1992, will include repairs to the substructure, and a new wearing surface. The contractor will have 30 calendar days to complete this repair. The bridge construction will be staged so that one lane will remain open with temporary signals.

Route 47 Bridge

The Mineral Fork Creek Bridge on Route 47, built in 1981 will also have staged construction with one lane remaining open with temporary signals guiding motorists through the work zone. Crews will replace the existing driving surface and expansion joints, repair concrete, and add a protective coating. The contractor is allowed up to 74 calendar days to complete this work. 

 


 

Project Progress

Complete
Planning and Design Phase

The Missouri Department of Transportation and its consultants designed improvements to extend the life of the bridges, including substructure repair, replacing expansion joints, concrete repair, and applying new driving surfaces. 

 

milestone_icon
Complete
Project Letting, Award, and Notice to Proceed

The project was part of MoDOT's April 2024 letting when contractors submitted competitive bids. At their May meeting, the Missouri Highways and Transportation Commission awarded the $1,091,402.40 contract to Concrete Strategies, LLC and issued a June 3, 2024, notice to proceed – the earliest date the contractor could begin work.

milestone_icon
Not Started
Project Construction, Traffic Impacts, and Completion

The construction crew anticipates beginning work in early June. From the first day of construction, Route 8 will have 30 calendar days to be completed and Route 47 will have 74 days to be completed. Traffic on both bridges will be narrowed to one lane with temporary signals during construction.

milestone_icon
Not Started
Project Completion

Work on both bridges is expected to be completed by mid-August 2024.

milestone_icon

Why is MoDOT rehabilitating the bridges?

The Route 8 bridge was built in 1992 and the Route 47 bridge in 1981. While both bridges are in good condition, there are routine repairs needed to several components - and deck sealing where needed – that will extend the usable life of each bridge.  While both bridges are in good condition, there are routine repairs needed to several components  - and deck sealing where needed – that will extend the usable life of each bridge. Once completed, motorists will have a smoother surface on which to drive.  

The construction on each bridge will be staged so that only one lane is closed at a time. Temporary traffic signals will be in place to guide motorists through the work zones. Delays can be expected during construction.

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Washington Route 47 & 8 Bridge Rehabilitations on your inquiries.

Sign up for project-specific updates using the form below.

Project News

  • Planned Road Work for Mid-Missouri

    01/31/2025

    JEFFERSON CITY, Mo. The following is a list of general highway maintenance and construction work planned in the midMissouri area Feb. 39, 2025. Weather conditions may postpone scheduled work. Many projects will include lane closures which could...

  • Planned Road Work for Mid-Missouri

    01/24/2025

    JEFFERSON CITY, Mo. The following is a list of general highway maintenance and construction work planned in the midMissouri area Jan. 27 Feb. 2, 2025. Weather conditions may postpone scheduled work. Many projects will include lane closures which...

  • Planned Road Work for Mid-Missouri

    01/17/2025

    JEFFERSON CITY, Mo. The following is a list of general highway maintenance and construction work planned in the midMissouri area Jan. 20 26, 2025. Weather conditions may postpone scheduled work. Many projects will include lane closures which cou...

  • Planned Road Work for Mid-Missouri

    01/03/2025

    JEFFERSON CITY, Mo. The following is a list of general highway maintenance and construction work planned in the midMissouri area Jan. 6 12, 2025. Weather conditions may postpone scheduled work. Many projects will include lane closures which coul...

  • Planned Road Work for Mid-Missouri

    12/27/2024

    JEFFERSON CITY, Mo. The following is a list of general highway maintenance and construction work planned in the midMissouri area Dec. 30 Jan. 5, 2025. Weather conditions may postpone scheduled work. Many projects will include lane closures which...

Webform
Sign Up for Project Updates via Email
*
*